Pedal sealer operation specification process

First, check and prepare before starting the machine:

1. Check that the power cord is secure and connected to the outlet.

2. Check if the heating wire and the insulation cloth are normal according to the working conditions.

3. Check if the machine parameters are normal.

4. Check that the lubrication of each rotating part is good, and inject a proper amount of lubricating oil.

Second, the operation:

1. Press the power switch first, then the green indicator light is on.

2. Rotate the knob of the heating time controller to point the pointer to (3) the required heating time value to start the sealing operation.

3. Put the assembled semi-finished product into the jig, put it in the foot and use the foot pedal (force 10kg or so); at this time, the red indicator light is on, and the force of the foot can be removed when the red indicator light is off.

4. Take out the product and check the welding effect. When the product is ok, place it on the assembly line for the next processing; when the product is NG, make the fusion until the product is OK before placing it on the assembly line for the next processing to complete the sealing operation.

Third, shut down:

1. Disconnect the power switch, the whole machine stops, and the green indicator light is off.

Fourth, maintenance and maintenance:

1. Change the insulation cloth every four hours to ensure the machine is working properly.

2. Once a week, replace the wearing parts (heating wire).